Equipment

The chargers we build with, matched to the site.

We carry a bench of manufacturers, so the hardware gets matched to the site rather than the site to the hardware. Every DC unit we install has a NACS cable, so Tesla drivers charge on all of them — and where the Tesla badge is itself the draw, we build Supercharger sites too. We size the kW to the dwell and the tariff, not to a quota.

Which charger for which site

Start with why people come to your site.

Power level follows dwell. A driver who's leaving in 20 minutes needs 200–400 kW; a diner or hotel guest who's parked for an hour fills up at 60 kW without the demand charge a 400 kW unit pulls onto your utility bill. Overnight is Level 2 territory.

Dwell decides the kW, and it also decides what the visit is worth to the rest of your property — the charger sells power, and the business already standing there sells whatever it sells in those minutes. Size the charger for the dwell you want, not just the dwell you have.

Oversizing is not only a bigger invoice. A charger bigger than the dwell time supports, or more units than your demand calls for, can set a peak on your power bill that the sessions never earn back.

Your siteHow long people stayHow long the charge takesClassUsual pick
Interstate exit, travel center, high-volume c-storeDrivers want in and out; turnover is the revenue.10–20 minThe stop is the bathroom and a coffee15–30 min350 kW+Dual-cable DC, NACS and CCSlike the SK-400, or a Tesla Supercharger where the badge draws
Shopping center, grocery-anchored strip, big-box, most c-storesHalf an hour of dwell steps from your tenants' doors.40–70 minA shop, an errand, a quick meal25–45 min200 kWDual-cable DC, NACS or CCSlike the SK-200, or a Tesla Supercharger
Restaurant, downtown lot, hotel, resortAn hour of dwell fills the battery; oversizing only raises the power bill.60–120 minA sit-down meal, an afternoon in town45–90 min40–60 kWDual-port DC, NACS and CCSlike the Topstar RC6000 or RC4000
Hotels overnight, apartments, workplacesParked for hours. Value beyond the meter.8–14 hoursOvernight, or the whole working day4–8 hoursLevel 2Level 2 AC, 7.2 to 19 kW, J1772 and NACSlike models from Topstar, Sarin Energy, Wallbox, Tap-N-Charge

Where the numbers land for your specific address — traffic, competition, and your utility's demand charge — is what the free evaluation and the working call are for.

The lineup

Specs, and what each one is for.

Fast-charging equipment is quoted, not listed. Pricing moves with configuration, volume and whatever promotions the manufacturers are running, so the honest answer is a current number from us rather than a stale one on a web page. Level 2 is different — it is a product you can simply buy, so those prices are here.

Either way the equipment is the smaller half. Installed cost depends on your electrical service, distance to power and civil work — a two-stall 200 kW build runs about $125,000 to $190,000, including the charger and site work, before incentives. What moves it between the two ends →

Flagship · 400 kW

SK Signet SK-400

400kW
High-traffic corridor sites where high speeds matter most.
SK Signet SK-400 dual-cable DC fast charger
Connectors
NACS + CCS1, two cables — or an optional four-cable build, 2×NACS + 2×CCS1, putting both connectors at each of the two stalls
Stalls per charger
Two
Serves
Every current EV, Tesla included
Branding
Custom options available
Software
Connect 10 for the full network, or Tap-N-Charge for credit card only
Quoted — ask for current pricing Tear sheet ↓two stalls, equipment only · manufacturer promotions move this
Talk to salesQuoted per site — power, civils and incentives change the number.
Workhorse · 200 kW

SK Signet SK-200

200kW
Most retail and some c-store builds. The unit behind the $125K–190K two-stall reference.
SK Signet SK-200 dual-cable DC fast charger
Connectors
Two cables. NACS or CCS1 — specified at order
Stalls per charger
Two
Serves
Every current EV, Tesla included
Branding
Custom options available
Software
Connect 10 for the full network, or Tap-N-Charge for credit card only
Quoted — ask for current pricing Tear sheet ↓two stalls, equipment only · $125K–190K installed for the two-stall build
Talk to salesQuoted per site — power, civils and incentives change the number.
Premium · brand pull

Tesla Supercharger V4

250kW / post
Corridor and retail sites where the Tesla badge itself draws traffic.
Tesla V3 Supercharger cabinet alongside a V4 post
Connector
NACS, with built-in Magic Dock CCS adapter for non-Tesla EVs
Vehicles per post
One — a post charges one car at a time
Sold as
Four-post systems, minimum four stalls — each stall has its own dispenser. 250 kW per car on the V3 cabinet
Software & service
Tesla's software and maintenance program. You set the price; Tesla keeps a share of every kilowatt-hour to cover software, payment processing and maintenance
Quoted — ask for current pricing Tear sheet ↓four-post minimum, equipment only — installation and make-ready are separate
Talk to salesQuoted per site — power, civils and incentives change the number.
Tesla's brand sits on the lot unless you wrap or rebrand it, which is your call. When Tesla is the right call, and when it isn't →
Dwell DC · 40–60 kW

Topstar RC6000 & RC4000

60 / 40kW
Restaurants, downtown lots, hotels, and resorts — an hour of dwell without a 400 kW demand charge.
Topstar RC6000 dual-port DC fast charger
Connectors
NACS + CCS1, dual port
Stalls per charger
Two
Why this class
Right-sized power keeps peak demand, and the utility bill, in line with what the site actually earns
Branding
Custom options available
Software
Connect 10 for the full network, or Tap-N-Charge for credit card only
Quoted — ask for current pricing Tear sheet ↓per charger, equipment only · manufacturer promotions move this
Talk to salesQuoted per site — power, civils and incentives change the number.
Level 2 · overnight and all-day

Tap-N-Charge

48 / 80A · 11.5 or 19.2 kW
Hotels, apartments, workplaces. Our own Level 2 charger.
Tap-N-Charge 80A dual-plug Level 2 pedestal
Connectors
One NACS and one J1772 cable on every unit, 18 feet each — both plug standards, nothing to specify
Payment
Drivers tap a credit card and charge — no app, no account
Access control
None — payment is required up front, at the posted rate. If particular people need free or reduced-fee access, that is Connect 10 instead →
Software
Its own platform, included with the unit: tap a card and charge, no recurring platform fee
Warranty
Two-year manufacturer warranty
Maintenance
VoltCare Exchange (parts) or VoltCare Response (parts and labour)
From ~$4,100 per dual-port unit Tear sheet ↓equipment onlyNetwork and payment: included for the life of the unit, no subscription
Add to cartBuy it online — no quote needed.
Level 2 · networked

EVS QC-910

32–80A · to 19.2 kW
The same dwell properties, when you need access rules rather than tap-and-pay — comped residents, staff at one rate, guests at another.
EVS QC-910 dual-plug Level 2 charging pedestal
Connectors
J1772 + NACS, dual port
Stalls per charger
Two
Output
Up to 19.2 kW per port, configurable at 32, 40, 48 or 80 A to suit the service you have
Access control
Named lists, tags and PINs — free, reduced or full rate by group
Warranty
Three-year manufacturer warranty
Maintenance
VoltCare Exchange (parts) or VoltCare Response (parts and labour)
Software
Connect 10: $199/yr per site plus $199/yr per charger
From ~$2,795 per dual-port unit Tear sheet ↓equipment onlyNetwork: Connect 10, $199/yr per site + $199/yr per charger
Talk to salesNeed help building it? Let our team help.

Also on the bench. When a site, a utility program, or a brand standard calls for a specific manufacturer, we source and install it at our pricing — the lineup above is what we reach for first, not the limit of what we'll build.

ABB · Blink · BTC Power · ChargePoint · Delta · Kempower · Sarin Energy · Tritium · Wallbox
Read before you pick a number

Four things the spec sheet won't tell you.

The car sets the speed, not the charger.

Most EVs on the road today peak at 150–250 kW and taper as the battery fills. A 400 kW charger doesn't make a 150 kW car charge faster; it keeps the site ahead of the next generation of vehicles. The charge-curve exhibit →

Demand charges can eat the margin.

On the wrong utility rate, the peak-kW charge on a 400 kW unit at a low-traffic site is the single biggest swing in fast-charging economics. We model your actual tariff before sizing the equipment. What a demand charge is, and what the software does about it → · How much it varies →

Stalls and chargers aren't the same count.

A two-cable DC unit serves two stalls; a Tesla post serves one, and Tesla systems start at a four-stall minimum with a dispenser at every stall. When you compare quotes, compare cost per stall and kW per stall, not the price of a single unit.

The charger is half the purchase.

A charger is hardware plus the layer that decides who may use it, what they pay, whether it's up, and where the money goes. That layer has a price, it recurs, and it is the easiest line to leave off a quote. When you compare quotes — ours included — ask for it in the same units as the equipment: what it costs per year or per kWh, and whether card processing is inside that number or billed separately. The four questions, and what each platform charges to answer them →

Those four are the whole reading list, and this page is the same page we'd hand you at a working call. Take it and buy your own chargers if that's the way you want to go — with the dwell table, the cost-per-stall rule and the tariff question, you can read anyone's quote, ours included. Or hand the address to us and we'll size it, build it, and run it. We'd rather be checked than trusted.

Get started

Which one fits your site?

Score the address free, then book a working call — we'll bring your utility rates and incentives and size the equipment with you.